KSC reported final preparations under way for moving the orbiter Columbia from VAB to pad A, Launch Complex 39, within the week. Mating Columbia in the VAB to its external propellant tank and solid-fuel rocket boosters November 24 was followed by tests of ground-support connections for checkout, fueling, and launch, and of the entire flight system. December 23 should see completion of the installation and checkout of ordnance (any explosive devices for parting components like the boosters and external tank from the vehicle in flight).

Gap-filler work needed before rollout would be complete by December 27; the crawler-transporter would take its place under the mobile launch platform December 28. Senior NASA managers would review the VAB tests and pad A status before rollout to make sure no constraints existed. (KSC Release 275-80)